QSP Practice Problems Part IV
Practice Questions
| Answers: |
Are there Risk catagories that do not require BMPs?
| No |
What are your minimum BMPs across all risk levels? |
Perimeter controls and stabilized entrances |
If you have a slope of 0-25% how frequent should you place slope interruption BMPs? |
20 feet |
If you have a slope of 25-50% how frequent should you place slope interruption BMPs? |
15 feet |
If you have a slope greater than 50% how frequent should you place slope interruption BMPs? |
10 feet |
Name four wind erosion controls. |
Water trucks, additives, limit disturbance, protect stockpiles |
What equation do you use to calculate estimated annual soil loss per acre on an unprotected site? |
RUSLE equation A=R*K*LS*C*P |
What is a CSMP? |
Construction Site Monitoring Program |
What is the CWA |
Clean Water Act |
What is an LUP? |
Linear Utility Project |
What is MS4? |
Municipal Separate Storm Sewer System |
What is NAL? |
Numeric Action Level (Yellow Light) |
What is NEL? |
Numeric Effluent Limit (Red Light - enforceable) |
What is NTU? |
Measure of turbidity (Nephelometric Turbidity Unit) |
What is a SWAMP |
Surfance Water Ambient Monitoring Program |
What is a WDID |
Waste Discharge Identification Number |
Where can the acryonyms be found? |
In Appendix 5 |