If you are planning on taking the PSP Certification offered by the Association for the Advancement of Cost Engineering (AACEI), you might be looking for studying material. You might be considering purchasing the Planning and Scheduling Peorfessional Certification Study Guide 2008 by Peter W. Griesmyer just like I did. Don't waste your money. This study guide is too broad and general to be of any use. It does not provide any details or definitions that would be key to becoming a certified PSP. Plus, there are a lot of frustrating copy and paste errors, wrong answers answers, missing answers, and the one example they did provide - their the critical logic ties are incorrect.
So in effort to make use of this book I will be posting an unofficial Errata for Mr. Griesmyer's Planning and Scheduling Peorfessional Certification Study Guide 2008. Contributions are welcome. Please post them in the comments field.
Planning and Scheduling Peorfessional Certification Study Guide 2008
Unofficial Errata (Update 1/20/09)
Page 33 -
So in effort to make use of this book I will be posting an unofficial Errata for Mr. Griesmyer's Planning and Scheduling Peorfessional Certification Study Guide 2008. Contributions are welcome. Please post them in the comments field.
Planning and Scheduling Peorfessional Certification Study Guide 2008
Unofficial Errata (Update 1/20/09)
Page 33 -
Delete the answer for 1.1.1-c.
Relabel 1.1.1-d to 1.1.1-c
Relabel 1.1.1-e to 1.1.1-d
Relabel 1.1.1-f to 1.1.1-e
Page 55 -
The answer for 1.2.2-f should read:
Information, function analysis, creativity, evaluation, development, presentation.
Page 223
Delete the answer to 2.3.2-a.
The for 2.3.2-a is b. Future change management. Change management should be accurately documented, but Future Change Management is not a consideration during schedule tracking.
Page 270
The question for 2.4.4-b should read:
What is the key factors in developing schedule forecasts?
There are two problems called 2.4.4-c. Relabel second question 2.4.4-c to 2.4.4-d
Page 295
Activity ID 1050 duration should be 25 WD.
Delete Activity ID 1050 Successor of 1010. Successor should be 1020.
Page 298
Activity ID 1030 should have a total float of 15.
Page 300
Activity #1200 successors are 1300, 1400, 1600
Please note that the NTP date is Saturday 3/1/2008
Labels: PSP Exam
Del.icio.us |
Digg it |
Reddit |
Yahoo MyWeb |
Google Bookmarks |
StumbleUpon |
Technorati Faves |
Blinklist |
Furl
1 Comments:
Pretty good post. I just stumbled upon your blog and wanted to say that I have really enjoyed reading your blog posts.
planning and scheduling
Post a Comment
Subscribe to Post Comments [Atom]
<< Home